  1. Single (1) Phase (Red -- Black -- Green-Ground)
  2. Three (3) Phase (Red -- Black -- Blue -- Green-Ground)
  3. Check Voltages across phases. (208 to 220)

Recommended amperage ratings:

Transmitter Wire Gage (CU) Cir Breaker/Fuse
1KW 12 AWG 20 A
2.5KW 10 AWG 40 A
5KW 8 AWG 50 A 3 PH
10KW 4 AWG 100 A 3 PH
25KW 2 AWG (480V) 100 A 3 PH
50KW 2/0 AWG (480V) 200 A 3 PH
  • The 3 Phase transmitters can be wired from either "Delta" or "WYE" sources. What is important is that voltage between phases matches transformer Taps.
  • +18V should be between 20 to 24V without the Power Amp panel(s) connected. Adjust the transformer taps if required on the low-voltage transformer.
  • If Red INTERLOCK LED is ON, check rear door(s) to make sure that they are completely closed and the interlock switches are completely depressed (See Figure 6). Also check that Remote Control Plug J9 - 1 is installed (See Figure 7).
  •  

    LED status on each power amp module...

  • Yellow 300VDC LED’s will Lite on each power amplifier module.
  • Scope will show a continuous Sine Wave. Note amplitude of wave form.
    1. Current reading on the 300VDC AMP meter.
    2. 300 Volt reading on the VOLT meter.
    3. Forward RF Power as indicated on RF % Power meter.
    1. 1 KW Transmitter 3.6 to 4.2 AMPS
    2. 2.5 KW Transmitter 9.0 to 11 AMPS
    3. 5 KW Transmitter 18.0 to 22.0 AMPS
    4. 10 KW Transmitter 38.0 to 46 AMPS
    5. All transmitters 300VDC should be in the range of 300 to 330 VOLTS
    1. +18VDC 18 to 19 VOLTS
    2. -18VDC 16 to 22 VOLTS

     

    Should you have any questions, please contact the factory:

    phone 610-825-4100

    fax 610-825-4047